Metal decking over is approximately 95% complete over both levels. Connections and fastening of the decking is not complete yet. Mechanical and electrical have resumed rough-in and stub ups at grade. Workers will be progressing through to the second floor in the next few weeks. Mechanical is continuing to install hangers for duct installation. Masonry work has commenced on site. The elevator shaft and stair B has been constructed.